Qatar Airways threatens to cancel Pratt & Whitney engine order
Qatar Airways threatened to cancel an order for Pratt & Whitney engines for a fleet of Airbus narrow-body jets on Tuesday
Qatar Airways threatened to cancel an order for Pratt & Whitney engines for a fleet of Airbus narrow-body jets on Tuesday, saying the newly developed power plants had “a lot of problems.”
The Gulf airline has ordered 50 A320neo-family aircraft and was originally due to take the first delivery in December, but rejected the jet due to what it called an engine problem and the first jet went last month to Lufthansa instead.
Asked at the Singapore Airshow to describe his concerns, Qatar Airways Chief Executive Akbar Al Baker said: “There are a lot of things wrong with A320neo, with the engines. So we have refused to accept those airplanes.
“Let me be very clear: it is not the fault of Airbus. Airbus has delivered all their part, and as you know, no airplane can fly without an engine. And they have huge issues with the engine,” he said in a group interview.
“I don’t want to get into the detail but Qatar Airways will not accept an aircraft with those engines unless they are very much corrected. Otherwise we have no alternative but to look at an alternate engine supply.”
Pratt & Whitney competes with CFM International, co-owned by General Electric and France’s Safran, to supply engines for the narrowbody Airbus jet family.
Pratt & Whitney has acknowledged teething problems on the engine but says they do not affect its 15-percent fuel savings.
“We will not cancel the A320neo order. Our relations with Airbus are very strong. We have full confidence in the neo program but yes, we could cancel the entire Pratt & Whitney order,” Al Baker told reporters.
Al Baker, who has a record of criticizing manufacturers at air shows over the airline's exacting quality standards, said engines had been delivered without the desired performance.
“According to them, they're on the way to correct these issues, but I have no confidence unless I see it really happen.”
Asked whether Qatar Airways had set a deadline for the problems to be resolved, he said, “Yes we have given them a deadline... Months.”
Pratt & Whitney officials could not immediately be reached for comment.
In an interview with Reuters earlier, Pratt & Whitney President Bob Leduc gave further details of two problems which have affected engine startup times and faulty engine software messages, but said these were being resolved.
Pratt & Whitney is delivering according to the latest schedule, he said.
Airbus and Pratt & Whitney officials said the schedule had been slowed in the first half of the year to ensure a smooth production ramp up.
Leduc said some 60-65 percent of the 200 Geared Turbofan engines that Pratt intends to build in 2016 would be delivered in the second half of the year.
-
Qatar vs. UAE: Who’s winning the battle for Gulf football supremacy?
There is a footballing arm’s race being contested in the Gulf, with both the UAE and Qatar competing - directly or not Sports -
Freed from sanctions, Iran’s airlines go on a spending spree
Within a fortnight of Implementation Day the flag-carrier signed a tentative order for 118 Airbus jets Aviation & Transport -
Iran to buy 118 Airbus aircraft worth $25 billion
The deal to purchase the medium- and long-haul planes was announced at a ceremony Aviation & Transport -
Airbus sold most jets in 2015, but Boeing delivered more
Chicago-based Boeing Co. says on its website that it took in 768 orders last year and delivered 762 aircraft Economy